What Is First Fix and Second Fix Electrics?
If you are planning a house rewire, a kitchen renovation, or an extension, you will hear electricians, builders, and plasterers talking about "first fix" and "second fix". Put simply: first fix is all the hidden cabling and back boxes done before the walls are plastered, and second fix is fitting the visible sockets, switches, lights, and fuse board once the plaster is dry.
Quick Summary: The Two Stages at a Glance
Lifting floorboards, chasing brickwork, drilling joists, running new cables, and fixing metal back boxes into the walls. Done before boarding, plastering, and tiling.
We step off-site while your plasterer skims the walls, the tiler tiles the splashbacks, the kitchen fitter installs the units, and you put your first coat of paint on.
Connecting socket faceplates, light switches, downlights, pendants, cooker connections, and the consumer unit, followed by live testing and safety certification.
Why Electrical Work Is Split Into Two Visits
You cannot screw a brushed brass socket onto wet plaster, and a plasterer cannot get a flat skim around a live switch hanging off the wall. Splitting the job into first and second fix keeps your cables safely buried behind the finish and leaves your new sockets, switches, and lights clean and unmarked.
What Happens During First Fix?
First fix is the structural groundwork. If you are stripping a kitchen back to brick, building an extension, or rewiring a whole house, this is when all the heavy lifting, drilling, and dust happen.
- ✓ Marking out: Walking every room with you to mark exact heights and positions for sockets, switches, wall lights, TV points, and kitchen appliances.
- ✓ Chasing walls & lifting boards: Cutting neat channels into masonry walls with dust-extracted wall chasers and lifting upstairs floorboards to access ceiling voids.
- ✓ Running cables: Pulling twin-and-earth power and lighting cables, 3-core switching cables, cooker feeds, shower feeds, and data/Cat6 cables back to the consumer unit position.
- ✓ Fitting back boxes & capping: Securing galvanised metal knock-out boxes into the brickwork and covering cable drops with protective capping so the plasterer can skim straight over them.
What Happens During Second Fix?
Once the plaster is completely dry, kitchen cabinets and worktops are in, and the walls have had their mist coat of paint, we return to connect everything up and bring the circuits to life.
- ✓ Sockets & switches: Dressing back the cables inside each back box and screwing on your chosen socket faceplates, USB outlets, dimmer switches, and cooker isolators.
- ✓ Lighting & appliances: Cutting holes for recessed LED downlights, hanging pendant lights, fitting under-cabinet LED strips, bathroom fans, and wiring ovens and hobs.
- ✓ Consumer unit termination: Connecting every new circuit neatly into an 18th Edition consumer unit with individual RCBO circuit breakers and surge protection.
- ✓ Dead & live testing: Testing continuity, insulation resistance, polarity, and RCD trip times before issuing your Electrical Installation Certificate.
How to Coordinate Your Plasterer, Kitchen Fitter & Decorator
The biggest headache on any home renovation is getting trades in the wrong order. Bring the plasterer in too early and we have to chop out fresh plaster to add a forgotten cable. Bring us back for second fix before the tiler has finished the splashback and the sockets will not sit flush. Here is the exact sequence that keeps a job running smoothly.
Finalise Your Plans & Kitchen Layout
Before we lift a tool, we need your finalised kitchen CAD drawing (showing exact positions of the hob, extractor, integrated fridge, dishwasher, and sink) and a clear idea of where beds, sofas, and TVs will sit.
Strip Out & First Fix Plumbing/Electrics
Old kitchens, tiles, and ceilings come down first. We then work alongside your plumber or heating engineer to run all first-fix pipes and electrical cables while joists and walls are open.
Plasterboarding & Skimming
Your plasterer boards the ceilings, fills the chases, and skims the walls right up to the edges of our metal back boxes. We fold our cables neatly inside the boxes so the trowel does not slice them.
Mist Coat Paint, Kitchen Units & Tiling
Once the plaster dries (usually 3–5 days), put your mist coat and first coat of paint on the walls while there are no sockets in the way. Kitchen fitters then install cabinets and worktops, and the tiler tiles the splashbacks.
Second Fix Electrics & Testing
We come back to fit all switches, sockets, downlights, under-cabinet LEDs, and hardwired appliances onto the finished surfaces. Everything is tested, labelled at the consumer unit, and signed off.
Carpets, Flooring & Final Touch-Up
Carpets and engineered wood flooring always go down after electrical work is complete so floorfitters do not trap boards we might need to lift during testing. Your decorator then does any final touch-up coat.
What If You Are Living in the House During a Rewire?
On an empty renovation site or a new extension, there can be several weeks between first fix and second fix while builders, plasterers, and kitchen fitters do their jobs.
However, if we are carrying out a full house rewire while you are still living in the property, we cannot leave you with bare cables sticking out of the walls for two weeks waiting for a plasterer.
How We Handle Occupied Rewires:
- • Temporary safe power every evening: We make sure you have working lights, fridge/freezer power, boiler power, and a charging station before we pack up each day.
- • Immediate second-fixing with basic white plates: We connect new white sockets and switches onto the back boxes immediately after chasing so every room is safe and live straight away.
- • Bonding chases flush: We can fill the cable chases with bonding coat plaster so your decorator or plasterer only has a small skim repair to do, gently loosening the faceplate screws when skimming.
First-fix cabling & temporary working lights on an active build.
Integrated appliances, plinth LEDs, and under-cabinet task lighting.
Building Regulations Part P Notification
New circuits, full rewires, kitchen/bathroom alterations, and consumer unit upgrades must comply with BS 7671 and be notified to local building control under Approved Document Part P. We handle the testing, certification, and building control notification at the end of second fix.
6 Things to Decide Before Your Electrician Starts First Fix
Once the plasterer has skimmed the walls, moving a switch by six inches or adding an extra LED strip means cutting into fresh plaster. Running through this checklist before day one saves time and money:
If you want ultra-slim screwless brass, black nickel, or dimmer switches, tell us at first fix. They need deeper 35mm or 47mm back boxes chased into the wall so the dimmer modules fit without pinching cables.
Know whether you are having a double, king, or super-king bed. A 150cm king bed versus a 180cm super-king changes where bedside pendant drops, reading lights, and sockets need to sit.
First fix is the cheapest time to run Cat6 ethernet cables from your router to a home office, loft room, or wall-mounted TV so you are not relying on patchy Wi-Fi through thick walls.
Backlit LED mirrors, demister pads, and electric toothbrush chargers need a cable brought out at the exact centre of the vanity unit before the bathroom tiler puts the tiles on.
Warm LED strip lighting in alcove shelves or under kitchen cabinets requires a small transformer (LED driver). We plan an accessible spot on top of a cupboard or inside a unit during first fix so it is easy to maintain later.
Even if you are not fitting an EV charger, garden office feed, or solar battery this year, we can run a heavy-duty supply cable under the floorboards before you lay new flooring down.
Related Services & Guides
Explore our rewiring services and practical electrical advice for your project.
Full & Partial Electrical Rewiring in Bristol
Professional full and partial electrical rewiring in Bristol, also covering Keynsham and Bath. We modernise old wiring, consumer units, and sockets for safety. Request a free survey.
What Size Solar Battery Do I Need for My Home?
Work out the right kWh solar battery capacity for your home based on your daily electricity use, solar panel size, and overnight energy tariffs.
How Much Does It Cost to Install a Home EV Charger?
Find out realistic UK costs for installing a home EV charger, and see how cable runs, fuse board space, and OZEV grants affect your final quote.
How Long Does a Fuse Box Replacement Take?
Find out what happens during a consumer unit upgrade, how long your power will be off, and how we handle wiring faults and Part P sign-off.
How to Prepare Your Property for an EICR Test
Use our simple EICR preparation checklist to get your home or rental ready. Learn how to clear access to your fuse board and sockets to avoid delays.
What Happens if Your Property Fails an EICR?
Find out what an unsatisfactory EICR report means in plain English, the 28-day rule for C1, C2 and FI repairs, and how to get your electrics signed off.
How Do You Know if Your House Needs Rewiring?
Learn how to spot the telltale signs of outdated wiring, from old rewireable fuses and black rubber cables to sockets in skirting boards and green goo.
How Often Do Businesses Need a Commercial EICR?
Find out how often your UK business needs a commercial EICR. We explain legal duties, testing intervals for offices and shops, and how inspections are planned.
Why Does My Fuse Box Keep Tripping?
Find out why your fuse box or RCD keeps tripping. Learn how to safely check for faulty appliances like kettles and when to call a qualified electrician.
Do You Need Planning Permission for Solar Panels?
Most UK homes don't need planning permission for solar panels. Learn how permitted development, conservation areas, and building regs apply to your roof.
Tethered vs Untethered EV Chargers: Which Is Best?
Compare fixed-cable convenience with socket-only neatness. Find out whether a tethered or untethered EV charger suits your home and driving habits best.
Do I Need Surge Protection on My Fuse Board?
Learn what a Surge Protection Device (SPD) does, why 18th Edition rules require them, and how they protect your boiler, EV charger, and appliances.
Is Upgrading Office and Shop Lighting to LED Worth It?
Find out how much replacing old fluorescent tubes with commercial LED panels and sensors can cut your energy bills, and what to expect during installation.
Planning a Rewire, Kitchen Refit, or Extension?
Speak directly to our team at Briggs Bray Electrical Services Ltd. We will walk the property with you, plan your first and second fix schedule around your builder and plasterer, and provide a clear, itemised quote.